Intel - Fab 52 and Fab 62

Project

*Intel

Project type

New Construction - Large Capital Construction of Semiconductor Factory

Core Contributions

Schedule Oversight, Risk Management, Time Impact Analysis, Schedule Analysis, Schedule Development




Construction Value

$20 Billion

Location

Chandler, AZ

Date

2021-2022

Industry

Technology

The construction of the Fab 52 and Fab 62 chip factories represents a landmark achievement in industrial infrastructure, marking the largest private-sector investment in Arizona’s history. This ambitious project focused on delivering two leading-edge semiconductor manufacturing facilities designed to push the boundaries of global domestic chip production. Given the unprecedented scale and technical complexity of the build, the project required a sophisticated integration of construction timelines and resource management to ensure the seamless delivery of these high-tech assets.

To maintain momentum, the focus was on supporting the Fab Construction Enterprise (FCE) by developing and managing the program’s high-level master schedules. This involved creating an integrated framework to monitor progress and mitigate potential bottlenecks across a complex web of construction activities. Acting as a central liaison between project leadership, clients, and subcontractors, the process ensured that everyone remained aligned on reporting requirements and emerging impacts. Through rigorous weekly quality assessments and schedule reviews, the project controls team provided the oversight necessary to keep the contractors’ performance synchronized with the program’s master goals, providing the technical backbone needed to execute a project of this magnitude.