Metro Bogotá
Project
*Metro in Bogotá
Project type
New Construction. Relocation of the underground utility lines for the construction of the metro
Core Contributions
Schedule Development, Cost Controls, Schedule Management, Acceleration
Construction Value
$ 5.2 Billion
Location
Bogotá, Colombia
Date
2020
Industry
Transportation
Managed the strategic scheduling and cost controls for the critical relocation of 24” and 16” potable water and sanitary sewer networks required for the construction of Bogotá’s First Metro Line. This high-priority utility diversion project covered approximately 6,500 feet along the Avenida Villavicencio corridor, necessitating precise coordination to clear the path for major transit infrastructure while maintaining municipal service continuity.
Led the elaboration of the project baseline schedule and spearheaded the implementation of innovative cost control methodologies to enhance fiscal transparency and performance tracking. Represented the project in high-level meetings with city officials to establish and align schedule update requirements with broader metropolitan infrastructure goals. By bridging the gap between technical utility engineering and municipal governance, ensured that the relocation remained on the critical path for the successful delivery of the city's new metro system.